Oil Platform Hook-up, Commissioning Contract for Kvaerner
ConocoPhillips confirms options in the Eldfisk 2/7 S topside contract for Kvaerner to perform offshore hook-up & commissioning assistance.
In March 2011, Kvaerner was awarded a contract by ConocoPhillips to perform engineering, procurement and construction (EPC) of the topside for the Eldfisk 2/7 S platform in the North Sea, with an estimated contract value of NOK 5.5 billion. ConocoPhillips has now confirmed options in the contract to perform offshore hook-up and commissioning assistance, which will add approximately NOK 400 million to the contract value.
The topside consists of one combined living quarter and utility module and a combined process and wellhead module, with a total weight of 15,500 tons. In addition, the contract includes the fabrication of two bridges, one bridge support module and a flare.
The offshore activities are planned to take place in 2013 for hook-up of the bridges and in the second half of 2014 for the topside modules.
The Eldfisk field is located in the Greater Ekofisk Area and has been in production since 1979. â¨Contract partner for the work is Kvaerner's subsidiary, Kvaerner Stord AS.â¨